APRIL 18, 2018

Portage Public Schools dives into second year of construction

Construction of Portage Central Natatorium, Portage North Middle School and Portage Northern's Huskie Stadium began in 2017 and continues to make major progress in 2018. Additionally, site preparations for the new Portage Central Middle School have officially begun.

Portage Central Natatorium

  • The pool is being water tested, a process that involves filling it up 1/3 at a time and waiting for 24 hours between each fill, to ensure there are no leaks.
  • Mechanical equipment for the new pool has been delivered and is ready for installation.
  • Taken in February, scaffolding was installed above the pool so crews could get to work on sound and lighting.
  • Also taken in February, crews worked above scaffolding to install sound panels, fabric ductwork, lights and paint the precast Ts.

Portage North Middle School

  • A concrete pump pours the mechanical penthouse floor
  • The concrete crew works on the mechanical penthouse floor
  • Masons build the south wall of the new gymnasium

Portage Northern's Huskie Stadium

  • Compaction around the goal posts and safety netting is complete. Crews finish the home team bleacher installation. The nearly complete concession building is being painted.
  • Long jump pits are filled and score board posts set. The stock pile of fines in the background will be spread on the field with a laser grader, on top of the 7" base that has already been laid. The base of the field is being leveled to ensure compaction, in preparation for turf installation next week! Home team lockers are in place. Next up, sealing and applying a rubber base to the floors.

In Other News

Ferriera Pablo

Owen‑Ames‑Kimball Florida Hires Pablo…

Owen‑Ames‑Kimball Florida Hires Pablo Ferreira as Estimator

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…
Clawson Edwin

Owen‑Ames‑Kimball Florida Hires Edwin…

Owen‑Ames‑Kimball Florida Hires Edwin Clawson as Project Manager

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…
3 presidents OAK

Gulf Coast Business Observer: $300…

Gulf Coast Business Observer: $300 million construction firm builds smooth succession plan

A nice dinner out paved the way for Owen‑Ames‑Kimball to…
Lux Robb

Owen‑Ames‑Kimball Florida Hires Robb…

Owen‑Ames‑Kimball Florida Hires Robb Lux as Superintendent

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…
Kellogsville 8

Kelloggsville Central Elementary Fun…

Kelloggsville Central Elementary Fun Facts

This new, 62,000 sf third through fifth grade building,…
Hudsonville 4

Tour Hudsonville High School with Jeff…

Tour Hudsonville High School with Jeff Weber and Jordan Beel

Currently under construction, this multi-phase expansion at…
Our Lady of Mercy Parish Life Center

Owen‑Ames‑Kimball Begins Construction…

Owen‑Ames‑Kimball Begins Construction on Our Lady of Mercy Parish Life Center

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…
Breaking Ground

Byron Center Breaks Ground on New…

Byron Center Breaks Ground on New Nickels Intermediate School

School board members, administrators, students, and project…
Trevor Anderson Matthew Gamalski James Griffith Josiah Kozicki

O‑A‑K Welcomes 8 New Employees

O‑A‑K Welcomes 8 New Employees

(Grand Rapids, MI) May 19, 2021 – Owen‑Ames‑Kimball Co.…
Coronado 2

Owen‑Ames‑Kimball Florida Begins…

Owen‑Ames‑Kimball Florida Begins Construction of Coronado Parkway Condominiums

Owen‑Ames‑Kimball Company (O‑A‑K), a preeminent general…