Meet PJ Riordan: Putting Students First in K12 Construction

Play Video
No items found.
February 7, 2023

O-A-K General Superintendent, PJ Riordan, has spent 32 years in construction. He started as an electrician while still in high school and worked alongside many contractors over the years. Along the way, he started thinking he could do the superintendent’s job himself.

When he talked with his wife about changing careers, she asked him a simple question: if he could go anywhere, where would he go? “It was pretty easy to say Owen-Ames-Kimball,” PJ says.

Today, PJ does a lot of remodel work, including his current project, a five-phase school renovation the team started planning more than a year ago. Construction in an occupied school brings its own set of challenges. “I think the biggest challenge is safety and separating construction from students and staff while they’re trying to still have school,” he says.

Noise is another one. PJ works to schedule drilling and cutting during off hours as much as possible, so learning can continue without interruption. “It takes a lot of prior planning to pull it off, and it takes a lot of working with the administration and the staff,” he says.

The school calendar shapes every decision. “In a school year, you really have three main starting and stopping points,” PJ says. “The only times you can really transition from one phase to the other.” Knowing that rhythm, he keeps an eye out for issues that need attention and adjusts on the fly when plans change. “You know that we’re going to have to take a U-turn here and try to figure out something different,” he says. “I think that’s where I’m good at construction.”

That ability comes from knowing the client. “O-A-K has a high standard of getting to know your client,” PJ says. “I’m always trying to take the client first and what the needs of the school are.” Because he understands each school’s standards, he can work through a situation and keep the project moving without delay.

That’s the approach we bring to every school we work in. Many of our field leaders came up through the trades like PJ, and they pair that hands-on experience with real relationships with the administrators, teachers, and facilities teams around them. It’s how we strengthen communities through thoughtful construction, one phase at a time.

Ready to put your experience to work on projects that matter to your community? Click here to view open positions, or reach out to our Talent Acquisitions Manager, Camila Gumati, at camilag@oakmi.com with any questions.

"I’ve worked with a lot of contractors over the years and thought I could do that job as a Superintendent. My wife asked me if you could go anywhere, where would you go? It was pretty easy to say Owen‑Ames‑Kimball."
PJ Riordan
Senior Project Superintendent
Owen‑Ames‑Kimball Co.

Related Stories

O-A-K Kalamazoo Breaks Ground on New Office

Last week, O-A-K team members, community leaders, and project partners gathered in Kalamazoo to break ground on our new Kalamazoo office. The building gives our Southwest Michigan team a permanent home designed around the way they work, collaborate, and serve clients across the region.

O-A-K first opened a Kalamazoo office in November 2013, starting with a small team in the historic Haymarket Building downtown. In 2024, we celebrated 10 years in the community. This new office is an investment in our employee-owners, our future in Southwest Michigan, and the community we are proud to call home.

Design partner Ghafari has helped shape a space that reflects who we are as a company and gives our team room to grow. Ghafari and O-A-K have a long history together, including our work on Ghafari’s own office in Grand Rapids.

Thank you to Ghafari, Western Michigan University (WMU), and Southwest Michigan First for their partnership and support, and to the leadership, project teams, and community representatives who joined us to celebrate.

October 29, 2026
Learn More

On Site at the New Forest Hills Aquatic Center

O-A-K Project Manager, Megan Wilson, and Cory Anderson, Director of Operations for Forest Hills Public Schools, walked the site to see how the district's new aquatic center is taking shape.

Located on the Dr. J. Michael Washburn Campus next to the Forest Hills Fine Arts Center, the project broke ground in December 2025 and is funded through the district’s 2023 bond, which voters approved in November of that year. Designed by TowerPinkster, the 77,813 sf facility features a nine-lane, 50-meter competitive pool and a four-lane, 25-meter community pool, giving the district the flexibility to run swim practices and community recreation at the same time. A separate dive well allows diving and swimming events to happen at once.

Those opportunities reach well beyond the district’s three high schools. The new center positions Forest Hills to welcome large events, from MHSAA state championship meets to national club swim meets, while expanding swim lessons, water fitness, and recreation for families across the community. The district’s current Community and Aquatic Center has served swimmers, athletes, students, and neighbors since 1990.

The aquatic center is one of several projects O-A-K is building alongside Forest Hills Public Schools, from school remodels to athletic facilities at each of the district’s high schools. “The partnership starts at design and goes all the way to completion,” Anderson said. “We spend a lot of time working together very closely to make sure these projects all come to fruition.”

O-A-K looks forward to turning over the new aquatic center to Forest Hills Public Schools in fall 2028.

Thank you to our video partners at Taproot Pictures for helping us tell this story.

October 27, 2026
Learn More

Kent District Library - Walker Branch Opens Its Doors

On Monday, October 19, the City of Walker and Kent District Library (KDL) officially opened the new Walker Library. Hundreds of community members gathered on the City Hall campus for a 9:30 a.m. ribbon cutting, and the doors opened to the public as soon as the ribbon was cut.

Mayor Gary Carey and KDL Executive Director Lance Werner kicked off the morning with remarks. Werner shared that the new library had been a topic of conversation for his entire 15-plus years with KDL. Pat Callahan of StudioGC and Josh Szymanski, PE, Chief Strategy Officer at O-A-K, also spoke, and the ceremony included a special thank-you to Meijer for its $1 million gift.

Opening day was also a homecoming for library staff, who spent 19 months serving patrons from a temporary location during construction. The celebration now carries on throughout the week, giving the public a chance to explore the new library, grab a bite to eat at one of the food trucks, and participate in activities like crafting and scavenger hunts.‍

Thank you to the City of Walker, KDL, StudioGC, Mathison | Mathison Architects (MMA), Meijer, and everyone who came out to celebrate opening day.

‍