Local joint venture team completes two major projects for Hope College

January 18, 2016

Local joint venture team completes two major projects for Hope College

Play Video

(HOLLAND, MI) - G.O. Construction, a local joint venture team composed of GDK Construction of Holland, and Owen-Ames-Kimball Co. (O-A-K) of Grand Rapids, is pleased to announce they have completed two major construction projects for Hope College; the new Jack H. Miller Center for Musical Arts and the new Kruizenga Art Museum.

Jack H. Miller Center for Musical ArtsThis 64,000 square-foot new construction project features a structure made of 65-foot tall precast concrete panels. Each panel weighs over 80,000 pounds, making the total weight of the concrete structure over ten million pounds. The structure was designed and built to isolate the transmission of sound and vibration from both the musical activities within the building, and from the adjacent rail tracks.

Other specialized components include a glass-enclosed two-story lobby area, an acoustically superior main performance hall with 800 seats (550 main floor and 250 balcony), an intimate recital hall with flexible seating for up to 125, new instrumental and choral rehearsal rooms, multiple faculty studios and practice rooms, and a dedicated organ studio.

Unique scheduling considerations were taken for the installation and tuning of the Casavant Opus 3903 organ. The organ was installed over a four-week span in June 2015. The facility opened to students in August 2015, while the main performance hall was in the final stages of completion. After the project was substantially complete, ahead of schedule in October 2015, five weeks were reserved to thoroughly and accurately tune the instrument.

The total project cost for Jack H. Miller Center was $35 million, which includes construction and an endowment for maintenance.

Kruizenga Art MuseumThe new Kruizenga Art Museum provides exhibition space for Hope College’s permanent art collection, a gallery for visiting exhibitions, and a central multi-purpose space for educational use and events. The building shell consists of 27 granite slabs, each soaring 22 feet high, with LED lights illuminating the space between each panel.

Other unique features include: A building footprint in the shape of an artist’ pallet; a Building Automation System (BAS) to monitor and control the heat, ventilation, and air conditioning system; full height entrance window with low-E coating; low-VOC paint in all interior spaces; steel beams in the ceiling to support potential hanging installations; and polished concrete floors.

The total project cost for Kruizenga Art Museum was $7.8 million, including construction and an endowment for ongoing building maintenance.

History of joint venture teamThe partnership between GDK and O-A-K initially formed in 2010, when they were hired by Holland Public Schools to manage $40 million worth of construction for three district facilities: Holland High School, West K-7 School and Jefferson K-7 School. In 2011, G.O. Construction was hired by a privately-held corporation along the lakeshore, to manage several additional projects. The joint venture team is currently working with Holland Township, West Ottawa Public Schools, and Zeeland Public Schools on several additional projects.

“If there is one thing our projects have in common it is that they are deeply intertwined with our West Michigan community. We are fortunate to have found a great niche in the community-driven market as we partner with our friends at GDK,” said O-A-K President and CEO, Frank Stanek. “We come to work every day and have fun.”

“The relationship between GDK and O-A-K is grounded in shared values. We are like-minded organizations, and we enjoy the challenges and successes of every project we complete together,” adds GDK President, Chuck Geenen.

Both Hope College facilities are open and operational for the 2016 winter semester. Architectural partners included HGA of Minneapolis (Jack H. Miller Center for Musical Arts), and C Concept Design of The Netherlands (Kruizenga Art Museum).

""

Related Stories

Castle Rock Fire Station 156 & Logistics Center Breaks Ground

Construction is underway on Castle Rock Fire Station 156 and a new Logistics Center, a project that will strengthen emergency response and support services for one of Colorado’s fastest-growing communities.

Owen-Ames-Kimball joined the Town of Castle Rock, Castle Rock Fire and Rescue, and project partners to mark the start of construction. As Construction Manager/General Contractor, O-A-K is working alongside RS&H and Dunakilly Management Group to deliver a facility designed to support both frontline response and the behind-the-scenes operations that keep it running.

The project combines a new fire station with a dedicated logistics and fleet maintenance facility—an investment aimed at improving response times, increasing operational efficiency, and ensuring first responders have the resources they need to serve the community.

“This station will help us continue to respond quickly when people need us most,” said Fire Chief Norris Croom. “Fire Station 156 strengthens our coverage in northeast Castle Rock and gives our crews the resources they need to serve residents safely and effectively.”

Early in the process, the team worked together to relocate the building outside of an existing floodplain. The adjustment introduced added complexity, including additional excavation, extended utilities, and the installation of a 30-foot soil nail retaining wall. By addressing these challenges during design and preconstruction, the team was able to maintain the building’s overall program while setting the project up for long-term performance.

Once complete, the facility will support the department’s Logistics Division and Fleet Support team, which oversees the maintenance and coordination of emergency response vehicles. The new station will also expand coverage for surrounding neighborhoods, helping the department keep pace with continued growth in Castle Rock.

This project reflects a shared commitment between the Town and its partners to invest in infrastructure that directly supports public safety and community well-being. O-A-K is proud to partner with Castle Rock Fire and Rescue and the broader project team to bring this facility to life.

April 16, 2026
Learn More

O-A-K Employee March Madness Event

Each year, our March Madness event brings our team together at the Operations Center for an afternoon of connection and celebration. From lunch and tournament games to golf simulator competitions, it’s a chance for our field and office teams to come together, strengthen friendships, and celebrate the work we do every day.

April 6, 2026
Learn More

Grand Rapids Archives Construction Update

Join O-A-K team members Dave Fleece and Trevor Anderson, along with Kristin Pfauth from the City of Grand Rapids, for a tour of the Archives & Records Center. While only about 10 percent of the city’s collection is on display at the public museum, the remaining 90 percent, over a quarter million items, are housed here at the archives.

This project will create a bright, open space designed for access and collaboration. Visitors will be able to request items, collector groups can gather, and teachers can bring students for hands-on learning experiences. One classroom will feature a retractable glass wall, allowing the space to be opened up or closed off as needed, while a permanent glass wall will offer visitors a direct view into the archives, connecting the public to the city’s rich history.

March 30, 2026
Learn More